Dutch Subsidiary Setup Timeline
Input your company profile and see a realistic, step-by-step timeline for establishing a Dutch BV — including the delays that nobody warns you about.
1 - 50 employees
Total estimated duration
Best case
7 weeks
Typical
5.7 months
Worst case
10.2 months
The reality check: Most US companies expect to be operational in 30 days. The realistic timeline is 5.7 months. The bank account is the critical path — everything else is blocked until it's open.
On track
Typical delays
Blocker risk
best/typical/worst